US utilities lift capex plans as data center load surges

· Energy · United States

Three major US investor-owned utilities used their third-quarter results to raise or refocus multi-year spending plans on the back of rapid data center demand growth. American Electric Power lifted its investment plan by 30%, citing contracted large loads up 22% to 84 GW, driven mainly by a 10.4-GW data center in Ohio being developed by SB Energy. Xcel Energy rolled out a $70 billion, five-year capital plan centred on renewables, including 9.2 GW of renewable capacity and 2.3 GW of storage. FirstEnergy said its data center pipeline rose to 26 GW in the quarter; two of its utilities reserved combined-cycle turbines for a 1.2-GW data center-focused project in West Virginia and issued a solicitation for a further 3 GW. The moves show how load growth from computing is reshaping utility planning and generation procurement.

Why it matters:Load growth from data centers is reversing years of flat US electricity demand and pushing utilities to commit record capital to both gas turbines and renewables, a shift that will shape equipment order books and grid investment for years.

Key points

  • AEP's contracted large loads rose 22% to 84 GW, led by a 10.4-GW Ohio data center from SB Energy
  • Xcel's five-year plan includes 9.2 GW of renewables and 2.3 GW of storage
  • FirstEnergy reserved combined-cycle turbines for a 1.2-GW West Virginia data center project

Sources (original reporting)

More stories from this day