US utilities add data center load by the gigawatt
· Energy · United States
US utilities reported sharp growth in their data center pipelines this week. American Electric Power raised its investment plan 30%, citing generation and transmission spending, and said contracted large loads jumped 22% to 84 GW, mainly on a 10.4-GW Ohio data center being developed by SB Energy. FirstEnergy's pipeline rose to 26 GW in the third quarter; two of its utilities reserved combined-cycle turbines for a 1.2-GW data center-focused project in West Virginia and issued a solicitation for another 3 GW. Separately, electrical equipment supplier Hubbell said data center purchases of its products are up 80% since 2025, though a temporary shortage of meter components should clear by year-end.
Why it matters:Data center demand is now the dominant driver of utility capital spending and equipment orders, reshaping grid planning and supply chains across the US.
Key points
- AEP's contracted large loads rose to 84 GW, up 22%.
- FirstEnergy reserved turbines for a 1.2-GW West Virginia project and sought bids for 3 GW more.
- Hubbell says data center purchases of its equipment are up 80% since 2025.
Sources (original reporting)
More stories from this day
- GE Vernova to buy Trench Group for $9B as gas turbine orders slow
- First Solar opens 1.7 GW module plant in South Carolina
- QatarEnergy signs 20-year US LNG deal with Woodside
- Nvidia in talks to backstop Nscale's $45B Anthropic data center
- Alphabet shares plunge about 13% in $500bn rout on AI concerns
- Rivian Q3 revenue jumps 38% as R2 becomes best-seller