Ohio approves gas plant for data centers as heat-battery alternative emerges
· Climate · United States
Ohio regulators approved construction of a large gas-fired power plant to supply a data-center complex, despite local voters' overwhelming rejection of the projects in this month's elections. The approval fits a wider US pattern in which energy-hungry data-center developers push ahead with their own fossil generation. Canary Media reported that such projects face sky-high equipment costs, years-long waits for backlogged gas turbines and growing public backlash over pollution. As an alternative, some developers are looking at giant heat batteries to deliver round-the-clock clean power to data centers. The Ohio decision shows regulators siding with supply demand over local opposition.
Why it matters:Data centers are becoming a decisive driver of new fossil generation, so how regulators balance local opposition against power demand will shape emissions and grid planning across markets.
Key points
- Local voters had rejected the data-center projects in this month's elections
- Developers face years-long waits for gas turbines
- Heat batteries are pitched as a 24/7 clean alternative
Sources (original reporting)
More stories from this day
- New York completes master plan for 5 GW of advanced nuclear
- Alabama gas pipeline explodes as owner seeks expansion
- US magnesium recycler cuts sulfur hexafluoride, a potent greenhouse gas
- Nvidia board reinstates Jensen Huang as CEO amid scandal
- Nvidia reinstates Jensen Huang as CEO; shares surge 31%
- FDA approves BridgeBio's BBP-418, first drug for limb-girdle muscular dystrophy