Grid operators file large-load interconnection reforms at FERC
· Energy · United States
Grid operators filed closely watched large load interconnection reforms at FERC, Utility Dive reported. PJM Interconnection proposed revamping its interconnection process by studying large load and generation interconnection requests in a single, one-year review. Other proposals focused on load flexibility, bring-your-own-capacity rules and cost transparency. The filings come as data centers and other large electricity users seek faster grid connections, putting pressure on interconnection queues that were largely designed for generators.
Why it matters:Interconnection rules determine how fast large new loads and generators can connect, shaping where data centers and industrial projects can locate.
Key points
- PJM proposed studying large load and generation requests in a single one-year review.
- Other proposals cover load flexibility, bring-your-own-capacity and cost transparency.
- The reforms were filed at FERC.
Sources (original reporting)
More stories from this day
- Google signs 50 MW superhot geothermal deal with Quaise Energy
- Siemens Energy sees elevated gas turbine demand persisting through 2035
- New York Power Authority names ten developers for advanced nuclear shortlist
- Nvidia board refuses to reinstate Jensen Huang after resignation
- Nvidia raises outlook after doubling revenue as CEO Jensen Huang exits
- Waymo halts highway rides nationwide after California DMV pause