Centrus and Oklo finalize fuel deal for five Ohio reactors serving Meta
· Climate · United States
Centrus and Oklo have finalized agreements securing fuel to power up to five Aurora powerhouses for multiple years at a 1.2 GW Ohio campus being built for tech giant Meta. The arrangement supports Centrus's capacity expansion plans and gives Oklo a supply line for its planned reactor fleet. The deal ties together two strands of the advanced nuclear buildout: Oklo's small fast reactors and Centrus's fuel production capacity. Data-center operators have become the anchor customers for a wave of new nuclear projects as they seek firm, low-carbon power. The agreements move the Ohio campus closer to construction and underline how hyperscaler demand is pulling fuel-supply investment forward.
Why it matters:Pairing a fuel supplier with a reactor developer and a hyperscaler customer shows how data-center power demand is becoming the commercial anchor for advanced nuclear, with ripple effects across the fuel cycle.
Key points
- The campus in Ohio is planned at 1.2 GW for Meta.
- Fuel would cover up to five Aurora powerhouses for multiple years.
- The deal supports Centrus's capacity expansion plans.
Sources (original reporting)
More stories from this day
- Bay Area finalizes first-in-nation zero-NOx rule for water heaters
- Microsoft 365 outage drags into second day; company blames bad update
- US Treasuries post worst week since 'liberation day'
- Iran Says Gas Tanker Hit Mine in Strait of Hormuz
- HHS funds up to $4.9M of ibogaine research for PTSD, addiction
- FAA halts all US departures nationwide over communications problem